Prevessin Computing Center (PCC) is getting out of the ground

On 22 April was held the first stone ceremony of the new Prévessin Computing Center (PCC). This project is undertaken and led by PPM group, and more especially Philippe Magnano, together with IT stakeholders: Wayne Salter and Olof Barring.

2022-09-16

Works on PCC

 

The PCC project is advancing at a good pace towards the completion of the main civil works and a watertight building expected mid-October. The impressive volume of the building has reached 20m high with its final 3rd level of concrete just completed. Ongoing activities include the connection to the technical galleries and external utilities. Onsite teams are preparing for the installation of the roof metallic structure, the façade cladding, secondary trades and mechanical and electrical activities all scheduled to start between October and November this year.

With the building shell almost complete and Monitoring and Evaluation activities in the starting blocks, all stakeholders involved are mobilised to begin testing in the summer 2023 and deliver a functional Data Center in autumn 2023.

Looking forward to this new innovative building!